// Add the new slick-theme.css if you want the default styling
In Ballard
v. Lee A. McWilliams Constr., Inc., No. 2160469, 2018 WL 670459, at *1
(Ala. Civ. App. Feb. 2, 2018), the Alabama Court of Civil Appeals determined
an award of prejudgment interest is due despite a defense that such damages
should not be recoverable given that they were not “certain” at the time of the
alleged breach due to the parties’ disagreement on the amount owed under the oral
cost-plus contract.
In
January 2010, Lee A. McWilliams Construction, Inc. (“McWilliams”) began
renovation work on a house owned by Angel Ballard (“Ballard”). Rather than
a fixed sum contract, Ballard and McWilliams orally agreed that she would pay the
company for the costs of materials plus 18%. Ballard failed to pay the full
amount of the final invoice and McWilliams filed suit. After judgment was
entered in favor of McWilliams for the unpaid portion of the final invoice, McWilliams
filed a timely postjudgment motion seeking prejudgment interest.
Alabama Code §
8–8–8 dictates interest is recoverable in contract actions “from the day such
money . . . should have been paid” through the date of judgment. The Alabama
Supreme Court has clarified that the right to prejudgment interest pursuant to this
section is only due “where
an amount is certain or can be made certain as to damages at the time of breach.” Ballard challenged McWilliams’s right
to prejudgment interest, arguing that “because the damages that the company had
requested changed during the litigation as a result of the discovery of certain
mathematical errors and other mistakes on the invoices”, the damages “were not ‘certain
or . . . capable of being made certain’ at the time of the breach.”
While the Court of
Civil Appeals agreed damages must be certain in order to be entitled to an
award of prejudgment interest, it held that a dispute as to how much is owed
does not prevent a determination that the damages are “certain.” Rather, once the amount of damages is fixed,
“§ 8-8-8 provides for prejudgment interest on that amount.” The Court concluded,
“although certain adjustments in the amount the
company claimed were made after completion of the discovery process, the
damages . . . were capable of being reasonably ascertained at the time of the
breach by mathematical computation (a tabulation of the outstanding costs of
the project plus 18%).”
This case is a good reminder for any party to a contract as
to what damages may properly be assessed if a judgment is entered against them.
While prejudgment interest is only recoverable if the amount due at the time of
the breach is certain and capable of being determined by a simple mathematical
computation, the Alabama Court of Civil Appeals construed the term “certain”
very liberally and award prejudgment interest even though the parties’ dispute arose
from not being able to agree on the amount actually due.