// Add the new slick-theme.css if you want the default styling
In Baker v. Rabren General
Contractors, Inc., 2020 WL 12145326 (M.D. Ala. 2020), the United States
District Court for the Middle District of Alabama analyzed whether an
arbitration provision in an unsigned subcontract was enforceable. Defendant
Rabren General Contractors, Inc. (“Rabren”) filed a Motion to Compel
Arbitration in the suit brought against it by Plaintiff Charles Baker (“Baker”),
pursuant to an arbitration provision in an unexecuted written contract drafted
by Rabren. The subcontract purported to be for concrete work by Baker on a
construction project Rabren had been awarded to build a new high school in
Auburn, Alabama (the “Auburn Project”).
Rabren and Baker had worked
together previously and had come to a mutual agreement that Rabren would
utilize Baker as its subcontractor for concrete work for all of Rabren’s
projects in Alabama. In exchange, Baker agreed not to bid against Rabren on any
projects.
Per this understanding, Rabren
hired Baker to do the concrete work on the Auburn Project for $952,157.00 in
September 2015. Although Rabren sent Baker a 44-page long subcontract for the Auburn
Project, neither party ever executed the subcontract. Nonetheless, Baker
proceeded to perform the work laid out in the subcontract. Baker eventually
left the Auburn Project around August 2016 due to Rabren’s alleged nonpayment
and purported hostility against Baker and his employees. Baker then submitted a
claim to Rabren’s surety.
Rabren demanded arbitration of
Baker’s claims based on the provision within the unsigned subcontract. Rabren
argued that Baker manifested his assent to the subcontract through his
subsequent actions and performance of work on the Auburn Project.
The Court focused its analysis on
whether the arbitration provision in the unsigned subcontract was enforceable
under Alabama law when the terms of the contract explicitly required the
parties’ signatures and initials on every page of the contract for it to be
valid. The Court noted that the purpose of a signature under Alabama law is to
show mutual assent, but counterargued that the Eleventh Circuit has found that
the Federal Arbitration Act (“FAA”) requires only that arbitration agreements
be in writing, not that they be signed. The Court further acknowledged that an
unsigned contract can be ratified through a party’s subsequent actions
manifesting assent to the terms of the agreement. Nonetheless, both state and
federal courts have refused to enforce arbitration provisions in contracts that
expressly require the parties’ signatures to be valid.
Here, the Court ultimately found that the parties’ partial compliance with some of the terms of the contract was not sufficient proof of Baker’s assent to be bound by the contract when the parties failed to strictly comply with the express requirement that the subcontract be signed and initialed in order to be valid. The Middle District of Alabama’s decision in this case serves as a warning to contractors who allow subcontractors to perform work prior to executing a contract in compliance with its express terms.