In Rankin v. South Street Downtown Holdings, Inc., 2019 WL 3562167 (N.H. Aug. 6, 2019), the New Hampshire Supreme Court addressed whether the state’s Statute of Repose applied to indemnity and contribution claims against architects, or only applied to claims for direct losses. The Court found the statute did apply and imposes a time limit on indemnity claims against architects.
In Demetro v. Dormitory Authority of the State of New York, 170 A.D. 3d 437 (N.Y. 2019), a New York Appellate Court addressed whether an architect’s failure to identify deviations from its designs subjected the architect to liability for personal injuries as a result of the defective condition. On a Motion for Summary Judgment, the Court found there was a genuine issue of material fact regarding whether a contractor’s deviation from the design, and subsequent failure to correct deviation, was an intervening and superseding cause which relieved the architect from liability.
In Novum Structures, LLC v. Larson Engineering, Inc., 2019 WL 1924878 (E.D. Wis. April 30, 2019), a Wisconsin District Court addressed whether an engineer’s sealing of design drawings makes the engineer the “Engineer of Record” and establishes a duty to verify the accuracy of the entire design. In 2014, Novum Structures, LLC (“Novum”) was hired to build a glass enclosed atrium. Novum prepared design drawings and supporting calculations for the atrium’s steel structure, but the drawings did not specify the type of welds that would be used to connect trusses to beams.
In Hayes v. Intermountain GeoEnvironmental Services, Inc., 2019 WL 2621931 (Utah Ct. App. June 27, 2019), the Utah Court of Appeals upheld the economic loss rule, finding a property owners’ tort claims against a geotechnical engineer were barred. In 2004, a developer hired Intermountain GeoEnvironmental Services, Inc. (“IGES”) to conduct a geotechnical investigation for a proposed subdivision. IGES concluded construction could proceed and the developer sold the lots to a third-party, who later sold an individual lot to Kim and Nancy Hayes (the “Hayes”) for construction of a home.
In D.R. Horton, Inc. – Jacksonville v. Heron’s Landing Condo. Assoc. of Jacksonville, Inc., 2018 WL 6803698 (Fla. 1st DCA Dec. 27, 2018), the District Court of Appeals of Florida, affirmed the trial court’s decision to allow expert testimony related to construction defects, even though the testimony was admitted pursuant to the Daubert standard, rather than the Frye standard. The Court held the expert’s opinion was admissible under both Daubert and Frye.
In Stapleton v. Barret Crane Design & Engineering, 2018 WL 985775, (2nd Cir. 2018), the United States Court of Appeals for the Second Circuit found that contractual privity, or its functional equivalent, did not exist between an owner and engineering firm retained by the design-builder, because there was no contract between the parties and the parties did not communicate directly to sufficiently “link” them.
In Engineering and Terminal Services, L.P. v. TARSCO and Orcus Fire Protection, LLC, 525 S.W. 3d 394 (TX 2018), the Court of Appeals of Texas held the statutory requirement to file a Certificate of Merit along with a lawsuit based on professional negligence of an engineer does not apply to third party claims for contribution.
In U.S. for benefit of Bonita Pipeline, Inc. v. Balfour Beatty Construction LLC, et. al., 2017 WL 2869721 (U.S. Dist. Ct., S.D. Cal.), the United States District Court for the Southern District of California ruled the Spearin Doctrine, in which an entity providing plans or specifications is liable for deficiencies in the plans or specifications, applies to subcontractors in design-build projects, even when plans or specifications are by definition meant to be further refined by the subcontractor.
In Triangle Construction Company, Inc. v. Fouche and Associates, Inc., 218 So. 3d 1180 (Mississippi 2017), Triangle Construction Company, Inc. (“Triangle”) contracted with East Madison Water Association (“EMWA”) to build a water system in Madison and Leake Counties in Mississippi. The contract designated Fouche and Associates (“Fouche”) as the project engineer, although Fouche was not a signatory to the contract. Triangle nevertheless argued Fouche was a party to the contract because Fouche’s seal was affixed to the contract’s cover, was designated as the project engineer and was designated as the agent and representative of the owner.
In Zirkelbach Construction, Inc. v. DOWL, LLC, 402 P.3d 1244 (Mont. 2017), the Supreme Court of Montana ruled design professionals can contract to limit liability for a contract claim, even if the limitation is a nominal percentage of the overall fees paid, as long as the parties do not disclaim all liability outright. However, the Court held that the limitation did not apply to the negligence claim in the suit.
In Curtis Engineering Corporation v. Superior Court of San Diego, 16 Cal. App. 5th 542 (Cal. App. Ct. 2017), the Court of Appeals for the Fourth District of California addressed the impact of the relation-back doctrine on the certificate of merit law in professional negligence actions against design professionals. California’s certificate of merit law, codified in the Business and Professions Code, Section 411.35, requires an attorney to consult with an architect or engineer in the same discipline before filing a complaint against a licensed architect or registered professional engineer and certify that, based on the consultation, there is reasonable and meritorious cause for filing the complaint. If an attorney is unable to obtain a consultation prior to the running of the statute of limitations, the law provides that a certificate of merit may be filed within sixty (60) days after the filing of the complaint.
In Sierra Court Condominium Association v. Champion Aluminum Corporation, 2017 IL App (1st) 143364, 75 N.E.3d 260 (Ill. Ct. App. 2017), First District Appellate Court of Illinois reaffirmed architects and engineering firms are not subject to the implied warranty of habitability of construction, even in the event the developer and general contractor are insolvent.
In Twist Architecture & Design, Inc. v. Oregon Board of Architect Examiners, 361 Or. 507, 395 P.3d 574 (Or. 2017), the Supreme Court of Oregon ruled that the “practice of architecture” includes the preparation of master plans drawn to scale for the development of a project, even if construction drawings or specifications are not ultimately produced.
In Sedgewick Homes, LLC v. Stillwater Homes, Inc., 2017 WL 3221488 (W.D. NC. 2017), the United States District Court for the Western District of North Carolina ruled there was a genuine issue of material fact as to whether Stillwater Homes, Inc. (“Stillwater”) infringed upon the copyrighted architectural plans of its competitor, Sedgewick Homes, LLC (“Sedgewick”). Sedgewick and Stillwater are home builders in North Carolina, who both interacted with two customers, the Bivins and the Shoemakers.
In Parkcrest Builders, LLC v. Housing Authority of New Orleans, 2017 WL 3394033 (E.D. LA. 2017), the United States District Court for the Eastern District of Louisiana held the Court could determine whether substantial completion had been achieved, despite a contract provision assigning this determination to the Architect.
In Sunset Beach Investments, LLC v. Kimley-Horn and Associates, Inc., 207 So. 3d 1012 (Fla. Ct. App. 2017), the Fourth District Court of Appeal of Florida held an engineering intern could not be liable for professional negligence. The Court explained an “engineer intern” could not be considered a professional because he does not maintain a license.
In Curtis v. Miss. Board For
Architects, Prof. Engineers, Prof. Land Surveyors, and Prof. Landscape
Architects, No. WD 80174, 2017 WL 2241516 (Mo. Ct. App. May 23, 2017), the
Missouri Court of Appeals affirmed the Missouri Board of Architects,
Professional Engineers, Professional Land Surveyors, and Professional Landscape
Architects’ (the “Board”) disciplinary order against an architect for violations
of a previous probation order. Donald
Dustin Curtis was an architect based in Arizona and licensed in multiple
jurisdictions, including Missouri. Mr.
Curtis’s license was placed on probation in Missouri for one year after he
failed to inform the Board of disciplinary action in Nevada. As part of his probation Mr. Curtis was
required to submit his plans for any projects in Missouri to the Board for
review.
In Melden & Hunt, Inc. v. East Rio Hondo Water Supply Corporation, No. 16-0078, 2017 WL 2492006 (Tex. June 9, 2017), East Rio Hondo Water Supply Corp. contracted with Melden & Hunt, Inc. to provide engineering-design and project-supervision services for a new water-treatment plant in San Benito, Texas. Following substantial completion of the project, East Rio complained about the quality of water treated at the plant and attributed the water-quality issues to the plant’s design and construction. East Rio subsequently filed a complaint against Melden & Hunt asserting claims for breach of contract, breach of express and implied warranties, negligence, and negligent misrepresentation.
In Corwin v. NYC Bike Share, LLC, No. 14-CV-1285, 2017 WL 1399034 (S.D.N.Y. Apr. 13, 2017), the Southern District of New York granted a Motion for Summary Judgment in favor of Alta Planning + Design + Architecture of New York, PLLC (“APD”) against the City of New York (the “City”) based on deviations from APD’s design of a bike share station which the Court concluded constituted an intervening cause of the alleged damage.
In United States of America v. Osborne, No. 4:11-CV-1029, 2017 WL 1135640 (N.D. Ohio March 27, 2017), the Northern District of Ohio denied a Motion for Summary Judgment filed by Third-Party Defendant William R. Gray Associates, Inc. (“Gray”) based on the permit procurement obligations in Gray’s agreement for engineering services with Third-Party Plaintiff City of Willoughby (the “City”).
In Levinson Alcoser Associates, L.P. v. El Pistolón II, LTD., No. 15-0232, 2017 WL 727269 (Tex. Feb. 24, 2017), the Supreme Court of Texas held Texas’s recently amended Certificate of Merit statute requires a plaintiff to accompany his complaint not only with a sworn Certificate of Merit from an expert stating the claim has merit, but also, the Certificate of Merit must demonstrate the expert has knowledge of the area of practice to which the complaint relates.
In Orchard, Hiltz & McCliment, Inc. v. Phoenix Insurance Co., Nos. 16-1176 & 16-1231, 2017 WL 244787 (6th Cir. 2017), the United States Court of Appeals for the Sixth Circuit affirmed a lower court’s grant of Summary Judgment against the Engineer, Orchard, Hiltz & McCliment, Inc. (“OHM”)...
In Sandlin v. Harrah’s Illinois Corp., 2016 WL 4585932 (App. Ct. Ill. September 2, 2016), the Appellate Court of Illinois (the “Appellate Court”) affirmed a lower court’s grant of Summary Judgment for Cross-Claim Defendant Hnedak Bobo Group, Inc. (“HBG”) dismissing Cross-Claim Plaintiff Harrah’s Illinois Corporation (“Harrah’s) claims for contribution.
In Town of Windsor v. Loureiro Engineering Assoc., 2016 WL 4007747 (Conn. Super. Ct. June 20, 2016), the Superior Court of Connecticut (the “Superior Court”) granted a Motion to Decide Questions of Law and to Dispense with a Jury Trial filed by Defendants Loureiro Engineering, Inc., Newman Architects, LLC, Herbert S. Newman, and Michael Raso (collectively, “Defendants”), the engineer and architects hired by Plaintiff the Town of Windsor (the “Town”) to design the Windsor High School auditorium.
In Venturedyne, Ltd. v. Carbonyx Inc., 2016 WL 3402807 (N.D. Ind. June 21, 2016), the Northern District of Indiana (the “District Court”) granted a Motion for Judgment on the Pleadings filed by Plaintiff/Counterclaim Defendant Venturedyne, Ltd. d/b/a Scientific Dust Collectors (“SDC”), an engineer hired by Defendant/Crossclaimant Carbonyx, Inc. (“Carbonyx”), to design and manufacture dust collection systems.
In Bd. of Managers of Film Exchange Lofts Condo. Ass’n v. Fitzgerald Associates Architects, P.C., 2016 WL 2841978 (Ill. App. May 11, 2016), the Appellate Court of Illinois consolidated three appeals and affirmed the lower courts’ decisions not to extend the implied warranty of habitability to architects. All three consolidated cases involved condominium boards bringing actions against architects for breach of the implied warranty of habitability, a claim typically alleged against the developer.
In Bronstein v. Omega Construction Group, Inc., 2016 WL 1577185 (N.Y. App. April 20, 2016), the Supreme Court of New York, Appellate Division, affirmed a lower court’s denial of a Motion to Dismiss filed by Defendant Michael T. Cetera, an architect hired by Plaintiffs to provide architectural services. In 2006, Plaintiffs entered into an agreement with Mr. Cetera to prepare plans for an addition to their residence.