Tennessee Court Of Appeals Upholds Judgment Holding That A Contract With A Target Completion Date And Start Immediately Language Contained An Implied Time Is Of The Essence Term
In Franks v. Bilbrey, the Tennessee Court of Appeals held that a construction contract containing a target construction completion date and the phrase “start immediately” contained an implied “time is of the essence” term, which the contractor breached by delaying completion well beyond the target completion date. No. M2021-00766-COA-R3-CV, 2022 WL 4588871, at *1 (Tenn….